A. Product risk
B. Project risk
C. Business risk
D. Programming risk
Explanation: Risks that affect the quality or performance of the software being developed.
Advertisement
Related Mcqs:
- What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk ?
- A. Risk monitoring B. Risk planning C. Risk analysis D. Risk identification...
- Which of the following is not considered as a risk in project management ?
- A. Specification delays B. Product competition C. Testing D. Staff turnover...
- Which of the following is not a business risk ?
- A. building an excellent product or system that no one really wants B. losing the support of senior management due to a change in focus or change in people C. lack of documented requirements or software scope D. losing budgetary or personnel commitment...
- Which of the following strategies means that the impact of the risk will be reduced ?
- A. Avoidance strategies B. Minimization strategies C. Contingency plans D. All of the mentioned...
- Which of the following is a collection of component versions that make up a system ?
- A. Version B. Codeline C. Baseline D. None of the mentioned...
- The expected value for the estimation variable (size), S, can be computed as a weighted average of the optimistic(Sopt), most likely (Sm), and pessimistic (Spess) estimates given as___________________?
- A. EV = (Sopt + 4Sm + Spess)/4 B. EV = (Sopt + 4Sm + Spess)/6 C. EV = (Sopt + 2Sm + Spess)/6 D. EV = (Sopt + 2Sm + Spess)/4...
- A 66.6% risk is considered as__________________?
- A. very low B. low C. moderate D. high...
- What all has to be identified as per risk identification ?
- A. Threats B. Vulnerabilities C. Consequences D. All of the mentioned...
- Which one is not a risk management activity ?
- A. Risk assessment B. Risk generation C. Risk control D. None of the mentioned...
- What is the product of the probability of incurring a loss due to the risk and the potential magnitude of that loss ?
- A. Risk exposure B. Risk prioritization C. Risk analysis D. All of the mentioned...